When a steel-anchor template shifts slightly before an encasement pour, what is prudent contractor guidance?

Choices

  • (A) Mask offsets with grout without telling anyone
  • (B) Hold work, notify engineer, survey offsets vs approved tolerances, then apply permitted correction paths
  • (C) Cold-bend anchors by eye until they look centred
  • (D) Pour immediately and inject later without a detail

Correct answer: (B)

Hold work, notify engineer, survey offsets vs approved tolerances, then apply permitted correction paths

Explanation

Documented deviations avoid unusable fittings after steel arrives.