Before staged reshoring of a young slab per engineer-approved sequence, what must first be tightly confirmed?
Choices
- (A) Paint color consistency on neighbouring slabs
- (B) Approved load-transfer sequence matches realistic construction loads on the slab
- (C) Heavier wet curing alone after one day without strength review
- (D) Assume timing from another project without checks
Correct answer: (B)
Approved load-transfer sequence matches realistic construction loads on the slab
Explanation
Staged stripping ties to engineered sequence and documented loads.