Before staged reshoring of a young slab per engineer-approved sequence, what must first be tightly confirmed?

Choices

  • (A) Paint color consistency on neighbouring slabs
  • (B) Approved load-transfer sequence matches realistic construction loads on the slab
  • (C) Heavier wet curing alone after one day without strength review
  • (D) Assume timing from another project without checks

Correct answer: (B)

Approved load-transfer sequence matches realistic construction loads on the slab

Explanation

Staged stripping ties to engineered sequence and documented loads.