A TAB report on a variable-air AHU in full balance typically documents which of the following as primary verifications of design intent (conceptual)?

Choices

  • (A) Only roof drain size
  • (B) Flow/ESP at setpoints, damper/terminal positions, total/min cfm, and kW/CFM in critical modes, within tolerances (e.g. 10%)
  • (C) Diesel generator only
  • (D) Blower door always

Correct answer: (B)

Flow/ESP at setpoints, damper/terminal positions, total/min cfm, and kW/CFM in critical modes, within tolerances (e.g. 10%)

Explanation

NEBB/TABB: OPR+design vs measured air/water+controls.